What was done this week:
This week was riddled with University Work. Had two major project
demonstrations.
So had to focus on them more. Anyway was able to finish export of baking of
constrained
animations on objects. Still have to test with other users. Also exporting
is done by frames of
target object animations. Will need modification.

What will be done in the next week.
- Importing constrained animations, what is exported now.
- More testing with user support.
- IK constraint animation support export and possibly import too.
- Update wiki on current progress.

Problems faced during the week:
- No serious problem for the past week.

Cheers,
phabtar
-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://lists.blender.org/pipermail/soc-2012-dev/attachments/20120609/d94a8462/attachment.htm 


More information about the Soc-2012-dev mailing list