What I did this week:
Slow week. Only worked at the start of the week. Identified the main problem
with the IK constraint export. It got to do with the basis change from IK
solving
doesn't get affected by different key frames. So went through the IK
solving process
in normal frame by frame solving. But couldn't finish it after that. Due to
two major
final year project deliverables at the end of the week, couldn't
concentrate in this
project so much.

What will be done next week.
The Final Year project is coming to a finish also. So have to balance this
work with
that project work. However doing my best to do them both together. So last
weeks due
work will be attempted to be completed.

Problems faced during the period.
Last weeks problems were somewhat subsided. But the IK constraint solving
problem
when exporting remains.

Cheers,
Phabtar
-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://lists.blender.org/pipermail/soc-2012-dev/attachments/20120721/d46d6e28/attachment.htm 


More information about the Soc-2012-dev mailing list