[Soc-2014-dev] Weekly Report #2 Interactive Quadrilateral Remeshing
Ton Roosendaal
ton at blender.org
Sun Jun 1 18:51:26 CEST 2014
Hi Alexander,
That is not satisfying for me. You even just copied the todo from last week to next week.
If you were completing university projects, you can just announce that in advance. If unforseen issues pop up at university, let us know.
Telling that this happened after a week is not acceptable.
I would like to see:
- reconfirmation of target
- description of midterm
- planning per week from now on.
You also are expected to be in irc, each day you work.
Thanks,
-Ton-
--------------------------------------------------------
Ton Roosendaal - ton at blender.org - www.blender.org
Chairman Blender Foundation - Producer Blender Institute
Entrepotdok 57A - 1018AD Amsterdam - The Netherlands
On 31 May, 2014, at 1:31, Alexander Pinzon Fernandez wrote:
> == What I did this week ==
>
> I apologize.
> This week was completing several projects at my university, and I could not advance the project.
>
> == Next week ==
> Define a way to display and store the initial scalar field.
>
> == Questions ==
>
> Att
> Alexander Pinzon
> _______________________________________________
> Soc-2014-dev mailing list
> Soc-2014-dev at blender.org
> http://lists.blender.org/mailman/listinfo/soc-2014-dev
More information about the Soc-2014-dev
mailing list