[Soc-2011-dev] dan_w weekly progress report 9 22/07/2011

Dan Walters dan683 at gmail.com
Sun Jul 24 17:20:14 CEST 2011


Dear all,

1) what you did this week

reviewed own progress following mid term

reviewed project plan

liazed with mentor over revising priority of each tool planned

arranged regular meetings

continued with extend and mesh from splines tool

2) what you will do next week

meeting with mentor to finalize a revised plan, will revise this week then

3) any problems that will require extra attention

My mentor and I are meeting later today to resolve.

Best wishes,

Dan
-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://lists.blender.org/pipermail/soc-2011-dev/attachments/20110724/7e5c3c5a/attachment.htm 


More information about the Soc-2011-dev mailing list