Dear all,
1) what you did this week
reviewed own progress following mid term
reviewed project plan
liazed with mentor over revising priority of each tool planned
arranged regular meetings
continued with extend and mesh from splines tool
2) what you will do next week
meeting with mentor to finalize a revised plan, will revise this week then
3) any problems that will require extra attention
My mentor and I are meeting later today to resolve.
Best wishes,
Dan