[Soc-2011-dev] Weekly Status Report 6 - 1 Jul - Garlic

xiangquan xiao xiaoxiangquan at gmail.com
Fri Jul 1 19:02:56 CEST 2011


1) This Week
- Complete most parts of wiki
- I think 80% texts have been covered, now. A little less than the expect in
last report, as I have taken three days off for the department's graduation
trip.

2) Next Week
- Release first demo in 3 days.
- Start the Chinese translation program with BlenderCN

3) Issues
- Nothing special, but a little busy these days.