Hi all,

With release branching for 2.83 coming up on April 15
and its release set on May 20 I am created the next
milestone project for 2.90 [1] with some dates. Following
the main release cycle phases [2] and the LTS post [3] from
Ton Roosendaal they currently look as follows:

Bcon1 April 15, 2020 (master)
Bcon2 June 10, 2020 (master)
Bcon3 July 8, 2020 (blender-v2.90-release)
Bcon4 August 5, 2020 (blender-v2.90-release)
Bcon5 August 12 20, 2020 (blender-v2.90-release)

I'd like to us to confirm these during the next developer
meeting on April 6. If you feel these dates are don't work
well for a reason please reply here with arguments.

Thanks,

/Nathan Letwory

[1] https://developer.blender.org/project/view/110/
[2] https://wiki.blender.org/wiki/Process/Release_Cycle
[3] https://code.blender.org/2020/02/release-planning-2020-2025/


More information about the Bf-committers mailing list