Dear Partners,

the final system specification (2.3) for the Uni-Verse project is due project
month 12, i.e. first of February. To reach this goal we have to start now.

The final system specification will of course be based on the current 
system specification (2.2) but has to be updated in the following ways:

1) Some points in the current specification is outdated and should be
updated by the responsible partner.

2) The current specification should be more specific on some points.
In some areas it might be possible to be more specific about the capacity
of the planned system i.e. how many polygons should it be possible to 
render a second.

3) It is also an advantage to organize each section in such a way that
results can be easily checked at the end of the project. (Checklist).

4) The demonstrators have to be more specific and it would be good to
write more about what demands they would place on the system.

WHO
Each WP-leader/partner is as earlier responsible for his section.

In a few days a specification will be sent out with comments on parts
which we think have to be updated.

WHEN
The idea is to collect the first round of updates until December 5 and 
have a computer conference meeting on December 13 starting at 13.00 MET.


Best Regards
Gert and Peter